The B1190 Bardney Road, Tupholme is getting improvements.
Resurfacing works will begin to replace the existing worn carriageway surface at the end of the month.
With a new surface in place, ride quality will be better for road users and the lifespan of the road itself will be greatly increased. The materials used will also reduce noise pollution caused by traffic on the route.
Location of works
The works will be carried out at B1190 Bardney road Tupholme, between Bucknall and Tupholme.
Dates and times
The works will begin on Monday, April 28 and have a scheduled end date of Thursday, May 15. The road will temporarily re-open for the local election on Thursday, May 1. Work times onsite will be from 07.30 to 17.00, subject to suitable weather.
No weekend works are planned.
Traffic management
Road Closures and Diversion Route will be in place during the works and will remain in place during working hours with local access maintained for residents.
The road will re-open again during the evening.
Diversion route
The signed diversion route will be; B1190 Bardney Road / B1202 Wragby Road / A158 Main Road / B1190 Thimbleby Road and vice versa.
For up-to-date information about this and other roadworks, please visit www.lincolnshire.gov.uk/roadworks.