Toynton All Saints stretch of A16 to be rebuilt

Toynton Diversion

Works to improve the A16 in Toynton All Saints will start in late April.

Karen Cassar, assistant director for highways, said: “Immediately following on from our ongoing A16 reconstruction works in Sibsey, we’ll be heading north to Toynton All Saints to rebuild another failing section of the A16. 

“This two-mile stretch of road will take up to a month to reconstruct, with up to 1,500 tonnes of road building materials set to be used.

“Please note that, as of now, we expect to start these works during week commencing 28th April. However, the actual day we break ground is dependent on when our resurfacing works in Sibsey are finished. This is because the same contractor and construction crew will be working on these improvements in Toynton All Saints, so any delays due to weather or other issues in Sibsey could affect when we start here. 

“Once a firm start date is confirmed, this will be posted on roadside signage so people are aware in advance.” 

Dates and timeframes

w/c 28th April for up to one month – actual start date will be displayed on roadside signage once confirmed

Location of works

A16, between A16/B1195 junction in Spilsby to and just north of the A16/Church Lane junction in East Keal

Traffic management

Night-time road closure from 7pm to 6am  (weekday evenings only)

Diversion route

Via A16 / A155 / A153 / A158 / A16, and vice versa

Karen Cassar added: “We'll be doing all we can to keep disruption to a minimum, including maintaining access for residents and emergency vehicles during our working hours.”
 
For up-to-date information about this and other roadworks, please visit www.lincolnshire.gov.uk/roadworks.

Published: 16th April 2025