An overview of progress on the Grantham Southern Relief Road project.
What we achieved in March
- East side of site – continued formwork, reinforcement and concrete works to the eastern abutment / concreted the ballast wall nib / installed steel-fixing to the wingwalls / shuttering and concreting to first wingwall for pour two
What's happening in April
- East side of site – continue formwork, reinforcement and concrete works to the eastern abutment / shuttering and concreting to north wingwall for pour two / shuttering to south rear wingwall for pour two / concrete finishing to the south face wingwall
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A
For more information about this project visit www.lincolnshire.gov.uk/gsrr.