Grantham Southern Relief Road March update

GSRR - Mar 2025 1

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in February

  • East side of site – completed temporary works to the platforms to Pier 4 / continued formwork, reinforcement and concrete works to the eastern abutment, including falsework and shuttering to the ballast wall 

What's happening in March

  • East side of site – continue formwork, reinforcement and concrete works to the eastern abutment / concrete the ballast wall nib / steel-fixing to the wingwalls / shuttering and concreting to first wingwall for pour two

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

For more information about this project visit www.lincolnshire.gov.uk/gsrr.

Published: 3rd March 2025