An overview of progress on the Grantham Southern Relief Road project.
What we achieved in February
- East side of site – completed temporary works to the platforms to Pier 4 / continued formwork, reinforcement and concrete works to the eastern abutment, including falsework and shuttering to the ballast wall
What's happening in March
- East side of site – continue formwork, reinforcement and concrete works to the eastern abutment / concrete the ballast wall nib / steel-fixing to the wingwalls / shuttering and concreting to first wingwall for pour two
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A
For more information about this project visit www.lincolnshire.gov.uk/gsrr.